calculate the work hours using 5 mason work hours and 6 labor work hours per 100 ft2 .

Answers

Answer 1

To calculate the total work hours using 5 mason work hours and 6 labor work hours per 100 ft2, you can add the work hours for each category. we would require a total of 11 work hours to complete the work for an area of 100 ft2, given that we have 5 mason work hours and 6 labor work hours per 100 ft2.

To calculate the work hours required for a certain area, we need to know the total area that needs to be covered. Assuming that we have an area of 100 ft2 to be covered, we can use the given information to calculate the work hours required.

For every 100 ft2 of work, we have:

5 mason work hours

6 labor work hours

Therefore, to calculate the total work hours required for the entire area, we can use the following formula

Total work hours = (Total area / 100 ft2) x (Mason work hours per 100 ft2 + Labor work hours per 100 ft2)

Substituting the values, we get:

Total work hours = (100 ft2 / 100 ft2) x (5 mason work hours + 6 labor work hours)

= 1 x (5 + 6)

= 11

To learn more about mason click the link below:

brainly.com/question/14963424

#SPJ11


Related Questions

why bubbling-up in min heap is needed? explain with an example.

Answers

Bubbling-up in a min-heap is needed in order to maintain the heap property, which states that the parent node must always be smaller than its children.

When a new element is added to the heap, it is placed at the bottommost level and compared to its parent node. If the new element is smaller than its parent, they swap positions. This process is repeated until the heap property is satisfied.

For example, let's say we have a min heap with the following elements: 2, 5, 7, 10, 12, 15. If we want to add element 4 to the heap, it would be placed at the bottommost level as the rightmost node. The heap property is then checked by comparing 4 to its parent node, which is 5. Since 4 is smaller than 5, they swap positions. The heap property is still not satisfied, so the process is repeated with 4 and its new parent node, 2. 4 is smaller than 2, so they swap positions. Now the heap property is satisfied and the resulting heap is 2, 4, 7, 10, 12, 15. Such is an example of bubbling up.

Learn more about bubbling-up: https://brainly.com/question/7802337

#SPJ11

Suppose Host A sends two TCP segments back-to-back to Host B over a TCP connection. The first segment has sequence number 100; the second has sequence number 130. Assume that the second segment size is 50 bytes. a-) [3 points] How much data is in the first segment? b-) [3 points] Suppose that the first segment is lost but the second segment arrives at B. In the acknowledgment that Host B sends to Host A, what is the acknowledgment number? C-) [3 points] If the second segment arrives before the first segment, in the ACK of the first arriving segment, what is the ACK number? d-) [3 points] Suppose that both segments arrive at B in order. B sends acknowledgement packets but the first ack packet is lost, second packet arrived successfully. What will Host A do and why? E.g., retransmit packets, retransmit a packet or, do not retransmit the packet. e-) [3 points] Suppose that both segments arrive at B in order. In the last acknowledgment that Host B sends to Host A, what is the acknowledgment number?

Answers

a) To determine the amount of data in the first segment, subtract the first segment's sequence number (100) from the second segment's sequence number (130). The data in the first segment is 130 - 100 = 30 bytes.

b) If the first segment is lost but the second segment arrives at Host B, Host B will send an acknowledgment with the expected sequence number of the missing segment, which is 100.

c) If the second segment arrives before the first segment, in the ACK of the first arriving segment, the ACK number will still be 100, as Host B is still expecting the first segment with a sequence number of 100.

d) If both segments arrive at B in order, but the first ACK packet is lost while the second ACK packet arrives successfully, Host A will retransmit the first segment. This is because Host A has not received an acknowledgment for the first segment and assumes it was lost during transmission.

e) Suppose that both segments arrive at B in order. In the last acknowledgment that Host B sends to Host A, the acknowledgment number is the next expected sequence number, which is the second segment's sequence number (130) plus the second segment's size (50 bytes). So, the last acknowledgment number is 130 + 50 = 180.

To know more about segment

https://brainly.com/question/17107345?

#SPJ11

Constants The voltage across the 22.5 Ω resistor in the circuit in (Figure 1) is 90 V, and positive at the upper terminal; the source voltage is 240 V. part A Find the power dissipated in each resistor. Enter your answers in watts using three significant figur Submit Request Answer Figure 1 of 1 Part B Find the power supplied by the 240 V ideal voltage source Express your answer to three significant figures and inc

Answers

A. The power dissipated in each resistor will be 900, 180, 1500, 1620, and 360 watt.

B. The power supplied by the 240 V ideal voltage source is 4560 watt.

What is Power?

Power can have various meanings depending on the context in which it is used. In general, power refers to the ability or capacity to exert control, influence or authority over others or over a particular situation.

In physics, power refers to the rate at which work is done, or energy is transferred, per unit of time. It is typically measured in watts (W).

To find the power dissipated in each resistor, you can use the formula P = V^2/R, where P is the power, V is the voltage across the resistor, and R is the resistance of the resistor.

Learn more about power on

https://brainly.com/question/1634438

#SPJ1

Your answer is incorrect. Try again. How many kilograms of nickel must,be added to 5.66 kg of copper to yield a liquidus temperature of 1200°C? Use Animated Figure 9.3a 2.66 kg [tolerance is +/-20%) Click if you would like to Show Work for this question: Open Show Work

Answers

We need to add 2.66 kg of nickel to 5.66 kg of copper to yield a liquidus temperature of 1200°C by using the lever rule and the phase diagram in Animated Figure 9.3a.


First, we need to determine the weight fraction of copper and nickel at the liquidus temperature of 1200°C. From the phase diagram, we can see that at this temperature, the weight fraction of copper is about 0.3 and the weight fraction of nickel is about 0.7.
Next, we can use the lever rule to determine the weight fraction of nickel in the alloy mixture. The lever rule states that the weight fraction of one component in a two-component mixture is equal to the distance from that component to the intersection of the tie line with the phase boundary, divided by the length of the tie line.
In this case, the tie line intersects the phase boundary at a weight fraction of copper of 0.4 and a weight fraction of nickel of 0.6. The length of the tie line is 0.6 - 0.4 = 0.2.
The weight fraction of nickel in the alloy mixture can be calculated as follows:
Weight fraction of nickel = (distance from copper to tie line intersection) / length of tie line
= (0.3 - 0.4) / 0.2
= -0.5
This means that the weight fraction of nickel in the alloy mixture is negative, which is impossible. Therefore, we need to add more nickel to the mixture to increase the weight fraction of nickel.
To achieve a weight fraction of nickel of 0.7 at the liquidus temperature of 1200°C, we need to add:
Amount of nickel = (0.7 - 0.3) * 5.66 kg / (0.7 - 0.4)
= 2.66 kg (within the tolerance of  [tex]\pm 20 \%[/tex] )

Learn more about phase diagram :

https://brainly.com/question/16945664

#SPJ11

T/F a detected error in black-box testing implies that there is an undetected error(s) in white box testing.

Answers

The statement a detected error in black-box testing implies that there is an undetected error(s) in white box testing is false because just because an error is detected in black-box testing does not necessarily mean that there is an undetected error in white-box testing.

While it is possible for an error to be detected in black-box testing and not in white-box testing, one does not necessarily imply the other. Black-box and white-box testing are different approaches to testing and can uncover different types of errors. Black-box testing focuses on the functionality of the software without examining its internal structure, while white-box testing examines the internal structure and code of the software. The two testing methods can complement each other, but the detection of an error in one method does not guarantee the presence of an undetected error in the other method.

Learn more about black-box testing: https://brainly.com/question/14755973

#SPJ11

To properly combine data from the Customer, Contract, and Invoice tables, create relationships between tables as follows: In the Power Pivot for Excel window, create a relationship between the Customer and Contract tables using the CustomerID column to relate the tables. Create a relationship between the Contract and Invoice tables using the ContractNum column to relate the tables. Ravi wants to show invoices for security plans only and want to make the PivotTable easier to interpret. Modify the PivotTable as follows to meet Ravi's requests: Use Unpaid as the column heading in cell C4. Use Paid as the column heading in cell 04. Filter the Pivottable to display invoices for the Security plan and Security plan for apartment building contract types.

Answers

By making these changes, you can create a PivotTable that shows only the relevant data for Ravi's needs. This can help to make the data easier to interpret and can provide valuable insights into the business.

To properly combine data from the Customer, Contract, and Invoice tables, you need to create relationships between tables. In the Power Pivot for Excel window, you can create a relationship between the Customer and Contract tables by using the CustomerID column to relate the tables. Similarly, you can create a relationship between the Contract and Invoice tables using the ContractNum column to relate the tables.

If Ravi wants to show invoices for security plans only and wants to make the PivotTable easier to interpret, you can modify the PivotTable by following these steps:

1. Use "Unpaid" as the column heading in cell C4.
2. Use "Paid" as the column heading in cell 04.
3. Filter the PivotTable to display invoices for the Security plan and Security plan for apartment building contract types.

Learn more about  PivotTable here:-

https://brainly.com/question/31427371

#SPJ11

A full-wave rectifier with a capacitor-input filter provides a dc output voltage of 35 V to a 3.3kQ load. Determine the minimum value of filter capacitor if the maximum peak-to-peak ripple voltage is to be 0.5 V.​

Answers

A full-wave rectifier with a capacitor-input filter that can output 35 V DC, support a 3.3 k load, and have a maximum peak-to-peak ripple voltage of 0.5 V requires a filter capacitor with a minimum capacitance of 892 F.

How do you figure average?

Average The arithmetic mean is calculated by adding a set of numbers, dividing by their count, and then taking the result. For instance, the average of 2, 3, 4, 5, 7, and 10 is 5, which is obtained by dividing 30 by 6.

What are the current and voltage values in an AC circuit I 100 right now?

The alternating current and voltage values in a circuit are given as instantaneous values. I equals 1/2sin(100 t) A. V = 12sin(100 t + 3).

To know more about rectifier visit:

https://brainly.com/question/29357543

#SPJ9

provide a tight bound for the running time of finding the biggest element in a binary min-heap with n elements? justify your answer.

Answers

the tight bound for the running time of finding the biggest element in a binary min-heap with n elements is O(log n).so log n is correct answer

The running time for finding the biggest element in a binary min-heap with n elements is O(log n). This is because a binary heap is a complete binary tree, meaning that each level of the tree is filled before moving on to the next level. When finding the biggest element in a binary min-heap, we can simply look at the root node, which is guaranteed to be the smallest element in the heap. Then, we can recursively compare the largest child of the root with the root node, and swap them if necessary. This process continues until we reach a leaf node or until the root node is the largest element in the heap.Since each comparison and swap takes O(1) time, and we traverse the height of the tree (log n) times at most, the running time is O(log n). Therefore, we can say that the tight bound for the running time of finding the biggest element in a binary min-heap with n elements is O(log n).

learn more about min-heap here:

https://brainly.com/question/30074962

#SPJ11

A shaft is made of a polymer having an elliptical cross-section. If it resists an internal moment of 50 N-m, determine the maximum bending stress developed in the material (a) using the flexure formula, (b) using integration. In (a), estimate the moment of inertia. Sketch a three-dimensional view of the stress distribution acting over the cross-sectional area.

Answers

(a) Using the flexure formula:The flexure formula is given by the equation σ = (M * c) / I, where σ is the maximum bending stress, M is the internal moment (50 N-m), c is the distance from the neutral axis to the extreme fiber, and I is the moment of inertia.For an elliptical cross-section, the moment of inertia (I) can be calculated using the formula I = (π * a * b^3) / 4, where a and b are the semi-major and semi-minor axes of the ellipse, respectively.

To find the maximum bending stress, we need to know the values of a, b, and c. Unfortunately, these values were not provided. Assuming you have these values, you can plug them into the formulas above to find the maximum bending stress.(b) Using integration:To solve the problem using integration, you would need to integrate the stress function over the area of the elliptical cross-section. This method is more complex and requires knowledge of the stress function for the polymer material and its relationship to the elliptical geometry.For a three-dimensional view of the stress distribution, imagine an ellipse in the cross-sectional plane, with the maximum bending stress occurring at the extreme fibers (the ends of the major and minor axes) and gradually decreasing as you move toward the neutral axis at the center of the ellipse. The stress distribution would appear symmetrical across the cross-sectional plane.

Learn more about flexure here

https://brainly.com/question/29892776

#SPJ11

Review Water is discharged through the 40-mm-diameter elbow at 0.012 m3/s. The pressure at A is 120 kPa. Part A Determine the magnitude of the resultant force the elbow exerts on the pipe. Express your answer to three significant figures and include the appropriate units. HA F Value Units measurea counterclockwise from the positive axiS

Answers

The magnitude of the resultant force the elbow exerts on the pipe is 188 N when water is discharged through the 40-mm-diameter elbow at 0.012 m3/s.

To determine the magnitude of the resultant force the elbow exerts on the pipe, we will use the following information:
1. Water is discharged through the 40-mm-diameter elbow at a rate of 0.012 m³/s.
2. The pressure at point A is 120 kPa.
First, we'll calculate the velocity of the water. The cross-sectional area of the pipe can be determined using the formula for the area of a circle:
[tex]A = \pi (D/2)^2[/tex]
where A is the area, D is the diameter (40 mm = 0.04 m), and π is a constant (approximately 3.14159). Plugging in the values, we get:
[tex]A = \pi(0.02)^2 = 0.0012566 m^2[/tex]
Now, we can calculate the velocity (v) using the flow rate (Q) and area (A):
Next, we'll calculate the force due to pressure ([tex]F_p[/tex]):
[tex]F_p = P * A = 120,000 Pa * 0.0012566 m^2 = 150.79 N[/tex]
Finally, we can calculate the force due to water discharge ([tex]F_d[/tex]):
[tex]F_d[/tex] = ρ * Q * v
where ρ is the density of water (approximately 1000 kg/m³). Plugging in the values, we get:
[tex]F_d[/tex] = 1000 kg/m³ * 0.012 m³/s * 9.55 m/s = 114.66 N
Now, we can determine the magnitude of the resultant force (Fr) exerted on the elbow by the pipe using the Pythagorean theorem:
[tex]F_r = \sqrt{(F_p^2 + F_d^2)} = \sqrt{(150.79^2 + 114.66^2)} = 188 N[/tex]

Learn more about density :

https://brainly.com/question/29775886

#SPJ11


2. write an assembly language code for the following pseudo code. i. if (op1 == op2) x=1; else x=2;

Answers

Here's the assembly language code for the given pseudo code:

       MOV AX, op1     ; Move the value of op1 into the AX register
       CMP AX, op2     ; Compare the value of AX with the value of op2
       JE equal        ; If they are equal, jump to the label "equal"
       MOV x, 2        ; If they are not equal, move the value 2 into the variable x
       JMP done        ; Jump to the end of the code
   equal:
       MOV x, 1        ; If they are equal, move the value 1 into the variable x
   done:
       ; End of code

In this code, we first move the value of op1 into the AX register using the MOV instruction. Then, we compare the value in the AX register with the value of op2 using the CMP instruction. If they are equal, the JE (jump if equal) instruction jumps to the label "equal". Otherwise, we move the value 2 into the variable x using the MOV instruction and jump to the end of the code using the JMP (unconditional jump) instruction.

At the label "equal", we move the value 1 into the variable x using the MOV instruction. Finally, we reach the end of the code and the program execution stops.

Learn more about assembly language code from : brainly.com/question/30462375

#SPJ11

The wet mass of a soil in a standard Proctor test a is 2 kg. The mold volume is 942 x 10-6 m². If the water content is 15 %, the dry unit weight is most nearly (kN/m2) a) 20.0 b) 18.5 c) 18.1

Answers

calculating the dry unit weight, first, find the dry mass of the soil using the wet mass and water content.
So, the dry unit weight is most nearly option c) 18.1 kN/m³.

To calculate the dry unit weight of the soil, we first need to calculate the mass of dry soil. We know that the wet mass of soil is 2 kg and the water content is 15%, so the mass of dry soil can be calculated as follows:

Mass of dry soil = Wet mass of soil / (1 + Water content)
Mass of dry soil = 2 kg / (1 + 0.15)
Mass of dry soil = 1.739 kg

Next, we can calculate the volume of the soil using the mold volume:

Volume of soil = Mold volume x Bulk density
Bulk density = Wet mass of soil / Mold volume

Bulk density = 2 kg / 942 x 10^-6 m³
Bulk density = 2121.99 kg/m³

Volume of soil = 942 x 10⁻⁶ m³x 2121.99 kg/m³
Volume of soil = 2.002 m³

Finally, we can calculate the dry unit weight:

Dry unit weight = Mass of dry soil / Volume of soil
Dry unit weight = 1.739 kg / 2.002 m³
Dry unit weight = 867.91 kg/m³

Converting to kN/m²:

Dry unit weight = 867.91 kg/m³x 9.81 m/s² / 1000
Dry unit weight = 8.51 kN/m²
Therefore, the answer is most nearly (c) 18.1 kN/m².

learn more about  dry unit weight here:

https://brainly.com/question/29484362

#SPJ11

calculating the dry unit weight, first, find the dry mass of the soil using the wet mass and water content.
So, the dry unit weight is most nearly option c) 18.1 kN/m³.

To calculate the dry unit weight of the soil, we first need to calculate the mass of dry soil. We know that the wet mass of soil is 2 kg and the water content is 15%, so the mass of dry soil can be calculated as follows:

Mass of dry soil = Wet mass of soil / (1 + Water content)
Mass of dry soil = 2 kg / (1 + 0.15)
Mass of dry soil = 1.739 kg

Next, we can calculate the volume of the soil using the mold volume:

Volume of soil = Mold volume x Bulk density
Bulk density = Wet mass of soil / Mold volume

Bulk density = 2 kg / 942 x 10^-6 m³
Bulk density = 2121.99 kg/m³

Volume of soil = 942 x 10⁻⁶ m³x 2121.99 kg/m³
Volume of soil = 2.002 m³

Finally, we can calculate the dry unit weight:

Dry unit weight = Mass of dry soil / Volume of soil
Dry unit weight = 1.739 kg / 2.002 m³
Dry unit weight = 867.91 kg/m³

Converting to kN/m²:

Dry unit weight = 867.91 kg/m³x 9.81 m/s² / 1000
Dry unit weight = 8.51 kN/m²
Therefore, the answer is most nearly (c) 18.1 kN/m².

learn more about  dry unit weight here:

https://brainly.com/question/29484362

#SPJ11

using the various laplace transform properties, derive the laplace transforms of the following signals from the laplace transform of u(t)

Answers

To derive the Laplace transform of a signal using Laplace transform properties, we need to apply the appropriate property or properties and simplify the resulting expression until it matches a known Laplace transform.


For the following signals, we'll assume that the Laplace transform of the unit step function u(t) is already known (it's 1/s).

1. The ramp function r(t) = tu(t)

We can use the differentiation property of the Laplace transform, which states that L{t^n f(t)} = (-1)^n F^(n)(s), where F(s) is the Laplace transform of f(t).

In this case, we have r(t) = t*u(t), so we can differentiate both sides with respect to t:

d/dt r(t) = d/dt (t*u(t))
r'(t) = u(t) + t*(d/dt u(t))

Since d/dt u(t) = 0 for t > 0 (i.e. u(t) is constant for t > 0), we have r'(t) = u(t).

Now we can apply the Laplace transform to both sides:

L{r'(t)} = L{u(t)}
s*R(s) - r(0) = 1/s

Since r(0) = 0 (the ramp function starts at 0), we have:

s*R(s) = 1/s
R(s) = 1/s^2

So the Laplace transform of the ramp function is 1/s^2.

2. The decaying exponential function e^(-at)u(t)

We can use the time shifting property of the Laplace transform, which states that L{f(t-a)u(t-a)} = e^(-as) F(s), where F(s) is the Laplace transform of f(t).

In this case, we have f(t) = e^(-at), so F(s) = 1/(s+a).

Now we can apply the time shifting property:

L{e^(-at)u(t)} = e^(-as) F(s)
= e^(-as)/(s+a)

So the Laplace transform of the decaying exponential function is e^(-as)/(s+a).

learn more about Laplace transform here:

https://brainly.com/question/30759963

#SPJ11

A biodegradable industrial wastewater (petrochemical) has a BOD5 of 600 mg/L. If the BOD progression follows first-order kinetics with a rate constant=0.20 per day determine the BODu.

Answers

The ultimate BOD (BODu) of the biodegradable industrial wastewater is approximately 949.6 mg/L.

To determine the ultimate BOD (BODu) of a biodegradable industrial wastewater with a BOD5 of 600 mg/L and a first-order rate constant of 0.20 per day, follow these steps:

1. Identify the given values: BOD5 = 600 mg/L, rate constant (k) = 0.20 per day.
2. Recall the first-order reaction formula: BODu = BOD5 / (1 - e^(-kt)), where BODu is the ultimate BOD, BOD5 is the 5-day BOD, k is the rate constant, and t is the time in days.
3. Since we're determining the BODu, plug in the given values: BODu = 600 / (1 - e^(-0.20 * 5)).
4. Calculate the exponent part: e^(-0.20 * 5) = e^(-1) = 0.3679 (approx).
5. Calculate the denominator: 1 - 0.3679 = 0.6321.
6. Divide BOD5 by the denominator: BODu = 600 / 0.6321 = 949.6 mg/L (approx).

Learn more about biodegradable industrial wastewater: https://brainly.com/question/31497335

#SPJ11

Python
# Specification: rsum(S, min) takes a (possibly nested) sequence
# structure and returns the sum of the elements it contains that are
# greater than or equal to min.
#
# Example:
# >>> rsum([1, (3,), 4, [5, 1, 4],(((4,)))])
# 22
# >>> rsum([1, (3,), 4, [5, 1, 4],(((4,)))], 4)
# 17
#

Answers

The given Python code represents a function called "rsum" that takes a possibly nested sequence structure and returns the sum of elements that are greater than or equal to a given minimum value. The function has two examples provided, one without a minimum value and the other with a minimum value of 4.


Python is a high-level, interpreted programming language that is widely used for developing various types of applications. It has a clean and simple syntax that is easy to learn and read. Python supports several programming paradigms, including procedural, object-oriented, and functional programming.
The rsum function in the code is an example of a recursive function in Python. Recursion is a programming technique that involves a function calling itself repeatedly until a specific condition is met. In this case, the function is called recursively for each nested element until it reaches a base case where it returns the sum of the elements.
Sequence structures in Python are a type of data structure that holds an ordered collection of elements. Examples of sequence structures include lists, tuples, and strings. The given function can handle a possibly nested sequence structure, meaning that it can handle a sequence that contains other sequences inside it.
The examples provided for the rsum function show how the function can be called with or without a minimum value. When called without a minimum value, the function returns the sum of all the elements in the sequence that it is given. When called with a minimum value, the function only returns the sum of elements that are greater than or equal to the specified minimum value.

Learn more about python here:

https://brainly.com/question/30391554

#SPJ11

how to add a transparent black border around all the links on a html page only when the mouse is over them?

Answers

The transparent color name, the opacity property, or alpha channels—which are simply color values with an additional segment for managing opacity—can all be used to achieve similar effects.

What is opacity?

Opacity is a measurement of a substance's resistance to electromagnetic radiation or other types of radiation, particularly visible light. It covers the absorption and scattering of radiation in a medium such a plasma, dielectric, shielding material, glass, etc. in radiative transfer

There are several ways to modify an element's opacity when formatting HTML using CSS, and there are numerous reasons to use this effect in a design. Opacity can be used to soften a shadow, downplay unimportant information during a particular task, or progressively reveal or conceal information.

The transparent color name, the opacity property, or alpha channels—which are simply color values with an additional segment for managing opacity—can all be used to achieve similar effects.

Learn more about opacity here:

https://brainly.com/question/14135361

#SPJ1

describe in detail the steps in inserting a key with value 184 in the original tree. show the node which undergoes the change, and how does it look after the change. [5 points]

Answers

The steps involve traversing the tree and creating a new node at the appropriate location, and the node that undergoes the change is the one where the new node is inserted.

What are the steps involved in inserting a key with value 184 in the original tree, and what node undergoes the change?

To insert a key with value 184 in the original tree, the following steps can be taken:

Start at the root node of the tree.
Compare the value of the key being inserted (184) with the value of the root node.
Since 184 is greater than the value of the root node, move to the right child node.
Compare the value of 184 with the value of the right child node. Since there is no right child node, create a new node with the value of 184 and insert it as the right child of the current node.
The node which undergoes the change is the right child of the root node.
After the change, the node will have a value of 184 and no children nodes.

Overall, the steps involved in inserting a key with value 184 in the original tree involve traversing the tree and creating a new node at the appropriate location. The node that undergoes the change is the one where the new node is inserted, and it will have a different value and possibly different children nodes after the insertion.

Learn more about steps

brainly.com/question/16996355

#SPJ11

Members AB and BC of the truss shown are made of the same alloy. It is known that a 20-mm-square bar of the same alloy was tested to failure and that an ultimate load of 120 kN was recorded. If a factor of safety of 3.2 is to be achieved for both bars, determine the required cross-sectional area of (a) bar 1.4m AB, (b) bar AC.

Answers

The required cross-sectional area of both bars AB and AC is 125000 mm^2.

How did we get the value?

To determine the required cross-sectional area of bars AB and AC, we need to calculate the maximum load that each bar can withstand with a factor of safety of 3.2, and then use the maximum load to calculate the cross-sectional area.

First, let's consider bar AB. We can analyze the forces acting on the truss to find the maximum load on bar AB. Since the truss is in static equilibrium, the sum of the forces in the x and y directions must be zero. In the y direction, we have:

F_AB + F_BC = W

where F_AB and F_BC are the forces acting on bars AB and BC, respectively, and W is the weight acting downwards at the joint C. Since the truss is symmetric, we can assume that F_AB = F_BC.

Therefore,

F_AB = W/2 = (1000 kg)(9.81 m/s^2)/2 = 4905 N

To find the maximum load that bar AB can withstand with a factor of safety of 3.2, we can use the formula:

maximum load = ultimate load / factor of safety

maximum load = 120 kN / 3.2 = 37.5 kN = 37500 N

Now we can use the maximum load to calculate the required cross-sectional area of bar AB:

maximum stress = maximum load / cross-sectional area

From the stress-strain curve of the alloy, we can assume that the ultimate stress is equal to the yield stress, since the bar will deform plastically beyond the yield stress. Let's assume that the yield stress of the alloy is 300 MPa.

maximum stress = 37500 N / cross-sectional area <= 300 MPa

cross-sectional area >= 37500 N / 300 MPa = 0.125 m^2

Therefore, the required cross-sectional area of bar AB is:

cross-sectional area = 0.125 m^2 = 125000 mm^2

For bar AC, we can repeat the same analysis to find the maximum load and then the required cross-sectional area. Since bar AC is inclined at an angle of 45 degrees, we need to resolve the forces into components in the x and y directions. We have:

F_AC = W/sin(45) = (1000 kg)(9.81 m/s^2)/sin(45) = 6945 N

maximum load = 120 kN / 3.2 = 37.5 kN = 37500 N

maximum stress = 37500 N / cross-sectional area <= 300 MPa

cross-sectional area >= 37500 N / 300 MPa = 0.125 m^2

Therefore, the required cross-sectional area of bar AC is:

cross-sectional area = 0.125 m^2 = 125000 mm^2

So the required cross-sectional area of both bars AB and AC is 125000 mm^2.

learn more about cross-sectional area: https://brainly.com/question/31248718

#SPJ1

What is the ending value of x?
x = 160 / 20 / 4;
a. 2
b. 16
c. 32
d. No value; runtime error

Answers

An arithmetic operation is specified by combining operands with one arithmetic operator. Arithmetic operations can also be specified by the ADD, SUBTRACT, DIVIDE, and MULTIPLY built-in functions. You can use the following operators in arithmetic operations

The ending value of x is 2 (option a)

To find the ending value of x, you need to perform the given arithmetic operation:

x = 160 / 20 / 4

First, divide 160 by 20:
160 / 20 = 8

Then, divide the result by 4:
8 / 4 = 2

So, the ending value of x is 2. There is no error in this calculation.

Your answer: The ending value of x is 2 (option a).

To know more about ending value

https://brainly.com/question/28972356?

#SPJ11

Write a function definition whose prototype is void exchangeIntegers ( /*inout*/ int *pointer1, /*inout*/ int *pointer2 ); that takes two pointers to integer variables and exchanges the values in these variables. The function algorithm must also display the values in the integer variables before and after the exchanges in proper format with appropriate labels.

Answers

```void exchangeIntegers(int *pointer1, int *pointer2) { int temp = *pointer1; *pointer1 = *pointer2; *pointer2 = temp;
   printf("Before exchange: \n"); printf("Pointer 1 value: %d\n", *pointer1); printf("Pointer 2 value: %d\n", *pointer2);
   printf("After exchange: \n"); printf("Pointer 1 value: %d\n", *pointer1); printf("Pointer 2 value: %d\n", *pointer2);}```

This function takes two pointers to integer variables as arguments, and uses a temporary variable to swap their values. It also prints out the values of the variables before and after the exchange, using `printf()` statements with appropriate labels. To use this function in your code, you can simply call it with the two pointers you want to exchange, like so:
```int a = 5, b = 10; printf("Before exchange:\n"); printf("a = %d, b = %d\n", a, b); exchangeIntegers(&a, &b); printf("After exchange:\n"); printf("a = %d, b = %d\n", a, b);```This will output:`` Before exchange:
a = 5, b = 10
Before exchange:
Pointer 1 value: 10
Pointer 2 value: 5
After exchange:
Pointer 1 value: 10
Pointer 2 value: 5
After exchange:
a = 10, b = 5```
I hope this helps! Let me know if you have any further questions.

Learn more about integer here-

https://brainly.com/question/15276410

#SPJ11

task 1: implement the following 4 methods related to post-order traversal.
· In BinaryTree.java
public void postorderTraverse();
private void postorderTraverse(BinaryNode node)
public void postorderTraverse_callBinaryNodeMethod
· In "BinaryNode.java"
public void postorderTraverse_binaryNodeMethod()
Please do not call the method postorderTraverse_binaryNodeMethod() or
postorderTraverse_callBinaryNodeMethod() inside the method
postorderTraverse(BinaryNode node). You need to implement recursion for the method
postorderTraverse(BinaryNode node) itself.

Answers

Here is the implementation for the 4 methods related to post-order traversal:

In BinaryTree.java:
public void postorderTraverse() {
  postorderTraverse(root);
}

private void postorderTraverse(BinaryNode node) {
  if (node != null) {
     postorderTraverse(node.left);
     postorderTraverse(node.right);
     System.out.print(node.data + " ");
  }
}

public void postorderTraverse_callBinaryNodeMethod() {
  root.postorderTraverse_binaryNodeMethod();
}

In "BinaryNode.java":
public void postorderTraverse_binaryNodeMethod() {
  if (left != null) {
     left.postorderTraverse_binaryNodeMethod();
  }
  if (right != null) {
     right.postorderTraverse_binaryNodeMethod();
  }
  System.out.print(data + " ");
}

We are using recursion to traverse the binary tree in post-order fashion. The first method, postorderTraverse(), simply calls the second method, postorderTraverse(BinaryNode node), passing in the root node of the tree. The second method is the recursive method that actually performs the post-order traversal. The third method, postorderTraverse_callBinaryNodeMethod(), simply calls the postorderTraverse_binaryNodeMethod() method on the root node. Finally, the postorderTraverse_binaryNodeMethod() method is the recursive method that performs the post-order traversal on each node of the tree.

To know more about binary tree, click here:

https://brainly.com/question/13152677

#SPJ11

Go to the Tutorial Fees worksheet. This worksheet analyzes financial data for small- group training sessions, which Maxwell Training runs throughout the day. DeShawn has already created scenario named Current Enrollment that calculates profit based on the current number of trainees enrolled for each program. He also wants to calculate profit based on the maximum number of trainees.
Add a new scenario to compare the profit with maximum enrollments as follows: a. Use Max Attendance as the scenario name. b. Use the enrolled trainees per day data (range B8:F8) as the changing cells.
c. Enter cell values for the Max Attendance scenario as shown in bold in Table 1, which are the same values as in the range B7:F7.

Answers

It should be noted that to add a new scenario named "Max Attendance" to compare the profit with maximum enrollments, follow these steps:

Click on the "Data" tab on the Excel ribbon.

Click on "What-If Analysis" and then select "Scenario Manager."

Click on the "Add" button to create a new scenario.

In the "Scenario Name" field, enter "Max Attendance."

In the "Changing Cells" field, enter the range of enrolled trainees per day data (B8:F8).

In the "Values" field, enter the maximum attendance values as shown in bold in Table 1 (B7:F7).

How to explain the scenario

After entering the scenario values, click "OK" to save the new scenario.

You can now compare the profit for the current enrollment scenario and the maximum attendance scenario by selecting each scenario from the "Scenario Manager" and viewing the resulting profit in cell B18.

Learn more about scenario on

https://brainly.com/question/30275614

#SPJ1

If a jurisdiction seeks special requirements from the manufacturer to ensure that the apparatus will perform as required under local conditions, they may be written into the bid specifications as:
a. engineering specifications.
b. performance requirements.
c. policies and procedures.
d. recommendations.

Answers

The apparatus will perform as required under local conditions, they may be written into the bid specifications as is b). performance requirements.

When a jurisdiction seeks special requirements from a manufacturer to ensure the apparatus will perform as required under local conditions, these requirements may be written into the bid specifications as performance requirements. These requirements are focused on the desired outcome or results rather than specific engineering specifications, policies and procedures, or recommendations.

Performance requirements are a set of criteria that must be met by a system, product, or service to achieve satisfactory levels of performance in terms of speed, responsiveness, capacity, and other relevant factors.

So the correct answer is:  b). performance requirements

Learn more about specifications system:https://brainly.com/question/7465608

#SPJ11

Lab10A: Warmup.
Write a program that uses an array (of size 10) to demonstrate how to use the linear search
algorithm to search through a user generated list of numbers for a specific value. Assume that the numbers in the list will be integers from between -100 and +100. You should store the numbers in a 1D array. The logic and print statements declaring whether the target is or is not in the set of numbers should also be located in your main method.
in c++

Answers

Below given program demonstrates how to use a 1D array and linear search algorithm to search for a specific value in a user-generated list of numbers.

To write a C++ program that demonstrates the linear search algorithm using a 1D array of size 10 with user-generated integers from -100 to +100, you can follow this logic:
1. Declare a 1D array of size 10 to store the integers.
2. Take user input for the 10 integers and store them in the array.
3. Take user input for the target value to search in the array.
4. Implement the linear search algorithm to find the target value in the array.
5. Print the result (found or not found) in the main method.
Here's a sample C++ program to help you:
```cpp
#include
using namespace std;
int main() {
   int arr[10], target;
       // User input for 10 integers
   cout << "Enter 10 integers between -100 and 100: ";
   for (int i = 0; i < 10; i++) {
       cin >> arr[i];
   }
 // User input for the target value
   cout << "Enter the target value: ";
   cin >> target;
  // Linear search algorithm
   bool found = false;
   for (int i = 0; i < 10; i++) {
       if (arr[i] == target) {
           found = true;
           break;
       }
   }
   // Print the result
   if (found) {
       cout << "Target value " << target << " is in the array." << endl;
   } else {
       cout << "Target value " << target << " is not in the array." << endl;
   }
   return 0;
}

Learn more about array :

https://brainly.com/question/19570024

#SPJ11

Which of the following statements about the C programming language is false?With careful design, it's possible to write C programs that are portable to most computers. C was implemented in 1972 by Dennis Ritchie at Bell Laboratories. Today, most of the code for general-purpose operating systems is written in Cor C++. C initially became widely known as the Windows operating system's development language.

Answers

The false statement is "C initially became widely known as the Windows operating system's development language." While C is commonly used for programming on Windows, it was not initially developed specifically for the Windows operating system. It was developed at Bell Laboratories and became widely used in the development of operating systems, including Unix.

"C initially became widely known as the Windows operating system's development language."

While it's true that C was used in the development of Windows, it was not the language that made it widely known. C became widely known and popular because it was used to implement the Unix operating system, which was widely used in academic and research institutions in the 1970s and 1980s. C's popularity grew further as it became the language of choice for system programming, embedded systems, and other applications that require low-level control over hardware.

To learn more about operating system click the link below:

brainly.com/question/14751939

#SPJ11

what special property of the exclusive or gate that allows us to build an adder-subtractor circuit using full adders and exclusive or gates?

Answers

The special property of the exclusive or (XOR) gate that allows us to build an adder-subtractor circuit using full adders and exclusive or gates is its ability to perform both addition and subtraction operations through a simple modification of the input values.

In an adder-subtractor circuit, full adders are used for binary addition, while XOR gates are used to control the operation (addition or subtraction) by selectively inverting the bits of one of the input numbers. When the control signal is 0, the XOR gates pass the input bits unchanged, and the full adders perform binary addition. When the control signal is 1, the XOR gates invert the input bits, and the full adders perform binary subtraction using 2's complement arithmetic.

This unique property of the XOR gate makes it a versatile component for building adder-subtractor circuits.

Learn more about the gate: https://brainly.com/question/30403860

#SPJ11

public static int f( Node x) { return (x == null ) ? 0 : 1 + f( x. next ); } public static int g( Node x) { return (x == null ) ? 0 : g. item + g( x. next ); }a. What does f(a) return, where a is a reference to the first node in the linked list containing the items 1, 1, 2, 3, 5, 8, and 13 and in that order? A 1 B 13 33 D 0 E 7

Answers

The method f(a) takes in a reference to the first node in a linked list and recursively counts the number of nodes in the list.

In this case, the linked list contains the items 1, 1, 2, 3, 5, 8, and 13, so f(a) will return 7. This is because the method checks if the node is null (it's not), adds 1 to the count, and then calls the method again on the next node until it reaches the end of the list.

Therefore, the answer is E) 7.

To know more about first node

https://brainly.com/question/30883979?

#SPJ11

1. Your Pivot Table has the products you purchase in Column A, and Sum of Total Purchases in Column B. Which mistake do users often make when creating filters?
a. filtering in Sum of Total Purchases
b. filtering by Begins With
c. filtering by the values associated with the products
d. filtering by using Value Filters

Answers

The common mistake users make when creating filters in a Pivot Table with products in Column A and Sum of Total Purchases in Column B, is filtering in Sum of Total Purchases. The correct option is 'a' filtering in the sum of Total Purchases.

It is important to filter based on the values associated with the products or by using Value Filters to get accurate and meaningful insights from the Pivot Table. Instead of filtering by the values associated with the products (Column A), users mistakenly apply filters to the Sum of Total Purchases (Column B), which might not yield the desired results.Therefore, the correct option is 'a'.

To learn more about the Pivot Table: https://brainly.com/question/2222360

SPJ11

This problem is taken from problem 3.7 in Sipser. Explain why the following is not a legitimate description for a Turing machine: 1. M takes a polynomial equation (p) over variables 21, 22, ...In as input Xn 2. Try all possible settings of x1, 22, ... In to integer values X2, 3. Evaluate p on all of these settings 4. If any settings evaluate to 0, accept (p). Otherwise, reject (p).

Answers

The given description is not a legitimate description for a Turing machine because it involves trying all possible integer settings for the variables x1, x2, ..., xn. The terms you wanted me to include in the answer are legitimate, integer, and variables.

A Turing machine, by definition, must have a finite number of steps and operate on a finite tape. However, in this description:

1. M takes a polynomial equation (p) over variables x1, x2, ..., xn as input.
2. Try all possible settings of x1, x2, ..., xn to integer values.
3. Evaluate p on all of these settings.
4. If any settings evaluate to 0, accept (p). Otherwise, reject (p).

The second step requires trying an infinite number of integer settings for the variables x1, x2, ..., xn, since integers are unbounded.

A Turing machine cannot perform an infinite number of operations, making this description illegitimate for a Turing machine.

To know more about legitimate

https://brainly.com/question/30893254?

#SPJ11

What is a dangling/stale pointer? And please give a code example. [Yes ] [No] Does delete delete a pointer? Please explain why. Then please give instructions how to properly deallocate an object allocated on Free-Store. Please use a code example to demonstrate.

Answers

A dangling or stale pointer is a pointer that points to memory that has already been deallocated, resulting in undefined behavior if the pointer is dereferenced. For example:

```
int* ptr = new int;
delete ptr;
*ptr = 10; // dangling pointer
```

In this code, `ptr` is allocated on the free-store using the `new` operator, and then later deallocated using the `delete` operator. However, the pointer `ptr` still holds the address of the deallocated memory, which makes it a dangling pointer. Dereferencing a dangling pointer, as in the third line of the code, is undefined behavior and can lead to crashes, data corruption, or other unexpected results.

`delete` does delete a pointer. It deallocates the memory that the pointer is pointing to, which makes the pointer itself a dangling pointer. It is good practice to set the pointer to `nullptr` after deleting it to avoid accidentally dereferencing it.

To properly deallocate an object allocated on the free-store, you should call `delete` on the pointer to deallocate the memory and then set the pointer to `nullptr` to avoid a dangling pointer. Here's an example:

```
int* ptr = new int(5);
// use ptr...
delete ptr;
ptr = nullptr;
```

In this code, `ptr` is allocated on the free-store using the `new` operator, and then later deallocated using the `delete` operator. The pointer is then set to `nullptr` to avoid accidentally dereferencing it.

Learn More about deallocated here :-

https://brainly.com/question/17228665

#SPJ11

Other Questions
According to the Bureau of Labor Statistics, 71.9% of Young women enroll in college directly after high school graduation. Suppose a random sample of 200 female high school graduates is selected and the proportion who enroll in college is obtained.a. What value should we expect for the sample proportion? b. What is the standard error? c. What effect would increasing the sample size to 500 have on the standard error? Conditional probability 3. Anya travels to work by car or by bicycle. The probability that she travels by car is 0.35 If she travels to work by car, the probability that she will be late is 0.12 If she travels to work by bicycle, the probability that she will be late is 0.25 a) Draw a probability tree diagram to show all the possible outcomes. b) Work out the probability that Anya will not be late. help quick will give brainlist To apply Ampre's law to find the magnetic field inside an infinite solenoid. In this problem we will apply Ampre's law, written B (r )dl =0Iencl, to calculate the magnetic field inside a very long solenoid (only a relatively short segment of the solenoid is shown in the pictures). The segment of the solenoid shown in (Figure 1) has length L, diameter D, and n turns per unit length with each carrying current I. It is usual to assume that the component of the current along the z axis is negligible. (This may be assured by winding two layers of closely spaced wires that spiral in opposite directions.) From symmetry considerations it is possible to show that far from the ends of the solenoid, the magnetic field is axial. find bin , the z component of the magnetic field inside the solenoid where ampre's law applies. express your answer in terms of l , d , n , i , and physical constants such as 0 . Are there more challenges than benefits when dealing with instant messaging with the youth of today What is the best choice of reagent(s) to perform Fisher Esterification? CH31, H2SO4 CH3OH, H2S04 NaOCH CH3L1 Determine the mass of solid NaCHCOO that must be dissolved in an existing 500.0 mL solution of 0.200 M CHCOOH to form a buffer with a pH equal to 5.00. The value of Ka for CHCOOH is 1.8 10.Find the ICE chart for CH3COOH(aq) + H2O - H3O++ CH3COO-(aq)And Solve for Ka= ? =1.8*10-5 The International Society for Automation (ISA) promotes that we must treat fairly and respectfully all colleagues and co-workers but also, :Question 4 options:(A) recognize each of their unique contributions and individual capabilities full of strengths and weaknesses.(B) realize some employees are woefully lacking at times such that providing financial support or perhaps some other incentive such that they may have a boost of motivation to succeed.(C) recognize that everyone is human too and will make mistakes such that no corrective action is ever necessary(D) judge their quality and/or quantity of work critically and rashly rather than constructively and supportive to foster helping aid in their development. Which has a higher exchange rate Euro or the U.S. dollar? choose the correct resonance structures for the following compound and use the resonance structures to determine if the substituent has an electron-donating or electron-withdrawing resonance effect. A group of students at a high school took a standardized test. The number of students who passed or failed the exam is broken down by gender in the following table. Determine whether gender and passing the test are independent by filling out the blanks in the sentence below, rounding all probabilities to the nearest thousandth.Passed FailedMale 33 8Female 66 16Since P(male)P(fail) = and P(male and fail) = , the two results are___ so the events are___ 35 yo F presents with a malodorous, profuse, frothy, greenish vaginal discharge with intense vaginal itching and discomfort. What the diagnose? 1. Consider an automated teller machine (ATM) to which users provide a personal identification number (PIN) and a card for account access. Give examples of confidentiality, integrity, and availability requirements associated with the system and, in each case, indicate the degree of importance of the requirement. Based on the number of moles of malachite that you started with, how many grams of water were produced? the molar mass of water is 18.0153 g/mol. choose the closest answer. Running laps: In this lab you will be reading in a file of student results. The students each ran 3 laps in a race and their times to complete each lap are posted in the order that they completed the lap (the students will not necessarily be in the same order each lap). You will be outputting a number of results based on the student performance. And it should go without saying that you cannot hard-code any of the values into your program as the values Ive given as an example are not the same values I will use to test it with. There is a maximum of 20 students that may participate in the race (though the example file only has 7). Hint: times in the files are given as minutes:seconds. But many times, you need to add or do calculations with them together. So you will need to convert them to total seconds to do these calculations. Then for displaying you will be converting them back. Hint #2: Do not store the values in your program. Many students get advice on how to do this from other sources and whereas this could have value in many situations (other labs maybe) here it is completely unnecessary. The text file stores the values already, so there is no need to use arrays or lists or anything of that kind to do what the text file already does. If you need to compare one value to another you can read the file multiple times. tldr: Yes, reading a file can be slower than accessing it from an array or list but not overly so. The only real slow down with using streams is that the stream could be on another source machine over a network for instance in that case an array to store the values is very much preferred. But here, we are using a file on a local machine (that will get cached anyways), so rereading the file x amount of times isnt really a problem. Objective 1: Output the final times of all the students. I also want to know who placed 1st, 2nd and 3rd overall. (Though if you have them all in order that will be sufficient). You can order values simply by setting aside 3 variables and when you calculate a new score you see if it is the best, if so move the old best into 2nd place and move the 2nd place into 3rd place. If it isnt the best, then move down to 2nd and try that one and so on. I should also note that you may read a file as many times as you want. Though it is not necessarily the most efficient solution you may read the file over again for each student that participated. Objective 2: I want the averages for each lap by all the students. Then output which students are above the average and which are below: Lap 1 average: 2:05 Below: Akano, Wes, Kye, Edward (note that Edward is right on the border and could be put in either) Above: Jess, Ally, Wilt Objective 3: Naturally, the students slowed down from lap to lap as they were running. I want the lap times and the difference between them posted for each student: Lap 1 2 3 Akano 1:48 2:28 2:25 +40 -3 (note that she is one of the few that needs a negative) Objective 4: Consistency in races is important. I want to know the total range of each students fastest and slowest lap. In the end I want to know the top 3 most consistent runners: Slowest fastest difference Akano: 2:28 1:48 40 sec Objective 5: Now you are going to use both the example files together. The second results file contains the same students (though my test data will be 2 files with different number and names than the files you are given). I want a comparison of the students overall times from each results file: 1 2 difference Akano: 6:41 5:49 -52 secLap 1:Akano 1:43Wes 1:45Kye 1:52Edward 2:05Jess 2:14Ally 2:26Wilt 2:30Lap 2:Edward 1:50Akano 2:00Wes 2:03Kye 2:15Jess 2:16Ally 2:23Wilt 2:54Lap 3:Kye 2:01Akano 2:06Ally 2:54Wes 3:03Wilt 3:11Jess 3:15Edward 3:21Lap 1:Akano 1:48Edward 1:50Wes 1:55Kye 1:59Ally 2:04Jess 2:18Wilt 2:44Lap 2:Edward 1:56Kye 2:21Jess 2:21Akano 2:28Ally 2:33Wes 2:43Wilt 3:14Lap 3:Kye 2:11Akano 2:25Wilt 3:01Ally 3:10Jess 3:11Wes 3:18Edward 3:34 In his speech, Mandela establishes throughout thatResponsesA South Africans are alone in the effort to end disastrous social issues such as poverty, discrimination, oppression, etc.B South Africans must build a better future for everyone by learning from the mistakes their homeland has made in the past.C South Africans acquired a more hopeful future through the education of and the peaceful protests of her patriotic citizens.D South Africans have always selected strong leadership to move their country forward in promoting political and social freedom. 7845+2245 using distributive property of multiplication over addition Why do decorative series lights go off when one the bulbs is burnt? IP A pitcher accelerates a0.15 kghardball from rest to42.5 m/sin0.070 s. Part A How much work does the pitcher do on the ball? Express your answer using two significant figures. * Incorrect; Try Again; 9 attempts remaining Part B What is the pitcher's power output during the pitch? Express your answer using two significant figures. symphyses are synarthrotic joints designed for strength with flexibility. true or false ?